The fastest way to power a new data center is to put it next to a power plant that already exists. That idea, called co-location, has been the hottest and most contested deal structure in the PJM region for two years. Federal regulators have now written the rules. In a December 18, 2025 order and a lengthy follow-up order on June 18, 2026, the Federal Energy Regulatory Commission told PJM exactly what data center co-location requires, and on November 16 PJM and its transmission owners made the filings meant to put those rules into the tariff.
If you are a developer, a generator owner or a landowner near a plant, here is what changed and the terms your contracts need to address.

What Data Center Co-Location Means
In a co-location arrangement, a large load such as a data center is built at or next to a generating plant and takes power directly from it. The appeal is speed: instead of waiting years for new grid capacity, the load uses a generator that is already interconnected.
The problem, as FERC framed it, is that PJM’s tariff never said what rules apply. In December 2025 the Commission found the tariff unjust and unreasonable because it did not address “with sufficient clarity or consistency” the rates, terms and conditions for generators serving co-located load. It also found that PJM’s existing retail behind-the-meter generation netting rules raised cost-shifting, reliability and resource adequacy concerns.
The rules matter in our backyard. Northern Illinois, served by ComEd, is in PJM, and ComEd is among the transmission owners in the proceeding.
Three New Transmission Services for Data Center Co-Location
Under the December order, the party taking transmission service on behalf of a co-located load must choose one of three options, as described in FERC’s June 18, 2026 order (195 FERC ¶ 61,209):
- Network service, including Interim NITS. Interim NITS is a new non-firm service available until the grid upgrades for full network service are finished. FERC agreed that customers have only an “option to seek” it, and found it reasonable to curtail Interim NITS during capacity or reserve shortages because those customers “do not pay generation capacity charges.”
- Firm Contract Demand. A firm service for a set amount of grid withdrawals. FERC directed that its rates be based on zonal network service rates.
- Non-Firm Contract Demand. A non-firm service for loads willing to be curtailed. FERC rejected PJM’s proposal to cap it at the firm rate.
A generator that wants to serve a data center without naming anyone to take grid service has one alternative: disconnect from the PJM system and run “fully islanded.”
Data Center Co-Location: 7 Critical Terms
- Who takes transmission service. The generator must identify an Eligible Customer that takes service for the load. Your power agreement should say who that is, who pays and who bears curtailment.
- Firm or non-firm. Interim NITS and Non-Firm Contract Demand can be curtailed. If your tenant’s uptime commitments assume firm power, the service election and the lease have to match.
- Upgrades come first. Under tariff language FERC accepted in June, an existing generator cannot begin serving co-located load until the network upgrades, special protection schemes and metering needed for reliability are in service, and the generator’s side pays for them.
- Capacity rights. An existing generator may not serve co-located load that is not network load until it has delisted its capacity interconnection rights for that portion of the plant. That affects plant revenue and any capacity commitments in your financing.
- Behind-the-meter netting. FERC accepted a 50 MW materiality threshold for retail behind-the-meter netting, with on-site backup power excluded and a three-year transition plus grandfathering for certain existing contracts. Above that line, a large campus can net only up to 50 MW of its load against on-site generation.
- Operational penalties. After a second failure to follow a curtailment or load-shed directive, PJM will terminate the service agreement. A first misoperation of required control or protection systems can suspend service for up to 120 days. Those risks belong in your operating and indemnity provisions.
- Timing. PJM proposed a June 1, 2029 start date for the new services, and FERC directed it to reconsider. The new rules are not yet fully in effect, so build regulatory conditions and outside dates into every agreement.
Where It Stands Now
The data center co-location rules are not finished. PJM made a partial compliance filing on August 17, 2026. On August 14, FERC granted a 90-day extension for the remaining directives to November 16, 2026, so they could be coordinated with FERC’s separate large load proceeding. According to POWER magazine, PJM and its transmission owners filed on November 16 alongside CAISO, MISO and NYISO, and those proposals “remain subject to FERC review.” PJM’s own summary of the December order is a useful plain-language starting point.
Our view: the specific rates and penalty terms in the November filings may change before FERC acts, so treat numbers you see reported as proposals, not final rules. Most of downstate Illinois, Missouri and Wisconsin sit in MISO, which is running its own large load process, so data center co-location deals there need a separate look.
How Co-Location Fits the Rest of the Deal
Data center co-location does not replace the rest of the project stack. A grid-connected site still faces a large load tariff with collateral and minimum-bill terms. Landowners near a plant should read our guide to the data center land lease before signing an option. Local approvals still run through data center zoning, incentives are covered in our post on data center tax incentives, and the cost-shifting fight behind all of this traces to rising data center energy costs.
What Developers and Generators Should Do Now
- Map your service election. Decide whether the load needs firm service and price the upgrade costs before you sign.
- Rewrite the power agreement. Allocate curtailment, upgrade costs, delisting and penalty risk between generator, load and transmission customer.
- Check existing behind-the-meter deals. Confirm whether your arrangement qualifies for the transition or grandfathering.
- Add regulatory conditions. Tie closing and rent start to FERC acceptance of the PJM filings and in-service dates for upgrades.
- Watch FERC. The Commission’s action on the November 16 filings will set the final data center co-location terms.
For the full development checklist, see our data center development practice page.